Project Overview: Alstom-Baden, a global leader in equipment and services for power generation, needed fire protection for one gas turbine in its test facility in Birr, Switzerland. In 2009, the company awarded Silvani, a UTC Climate, Controls & Security company, a contract to install a safety system that will integrate fire detectors from Det-Tronics and a water mist system from Marioff. The work is scheduled for completion in September 2010.



Case Study of Alstom


Solution: Fire safety is a critical issue for power plant operators, and there are many regulations in place to ensure that a facility is protected from fire. With an extensive history in gas turbine protection, UTC Climate, Controls & Security is well positioned to meet those requirements. For the facility at Birr, Alstom-Baden selected UTC Climate, Controls & Security to provide a fire detector and water mist system, based on its engineering expertise, its knowledge of fire safety, and its technologies. Click here to find out more on Alstom Case Study



Register to mark your Comments


Comments

Filed under Assorted, Industry Specific Cases